PROJECT: Port Diana, Luxury Apartments
LOCATION: Portstewart
CLIENT: Private
MAIN CONTRACTOR: Private
CONSULTANT: Newline Architects & Studio Rodgers
CONTRACT PERIOD: 12 months
A new build property development in a prime location within Portstewart overlooking the Harbour & Sea. HM Electrics worked closely with the client and consultants to complete this project to a high and efficient standard to compete in the demands of today’s clients as they search for high specification turnkey finishes. This installation consisted of a full liaison with NIE supply power to the property. We then supplied and installed all electrical switchgear and distribution equipment fitting out each apartment with top of the line specification electrical products. These luxury apartments come complete with and up-to-date fire, security, and CCTV systems. Externally finished with feature lighting. HM Electrics Ltd successfully tested and commissioned the project with handover to the client in July 2018.